Under construction

Prime OpalMahaRERA P52000048900

by Prime Abhishek Buildcon

Plot No. F-11 236, Sector - 3, Dapoli , Pushpak Node, 410206

Dec 2026
Possession
46.4%
Built
1
Complaints
33
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 46.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52000048900
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2024
Construction
46.4% complete
Units sold
26 of 33

RERA complaint record1 record

  • ComplaintCC126034976 Jun 2026
    KARAN SHAH vs Prime Abhishek Buildcon

Landowner

Vithabai Ganpat Waskar

Possession extension history

  • EXT52000027488Revised to June 2025

    We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 30-06-2025 to complete the project and fulfil all regulatory requirements. We seek your understanding and approval of this request.

  • EA19012619505Revised to June 2026

    We request a RERA extension due to pending Occupancy Certificate (OC) formalities. The project construction is completed; however, certain statutory inspections, documentation reviews, and approval processes by the designated authorities are still underway. These procedures are beyond the control of the promoter and require additional time to ensure full compliance with regulatory requirements. Therefore, an extension is sought to complete the OC process and hand over the units lawfully. Given the circumstances, we kindly request an extension until 30-06-2026, to complete the project and fulfil all regulatory requirements.

  • EA20072621802Revised to December 2026

    We hereby request an extension of the project registration period due to the pending issuance of the Occupancy Certificate (OC). While the construction of the project has been completed, certain statutory inspections, documentation verifications, and approval procedures by the competent authorities are still in progress. These regulatory processes are beyond our control and require additional time to ensure full compliance with all applicable legal and statutory requirements. The extension is therefore sought solely to facilitate the completion of the OC formalities and enable the lawful handover of units to the respective allottees. In view of the above circumstances, we kindly request the Authority to grant an extension of the project registration until 31-12-2026, to allow sufficient time for obtaining the Occupancy Certificate and fulfilling all remaining regulatory obligations

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jan 2023
Floors
7
Unit mix
29 res ยท 4 comm
Plot / CTS / survey no.
Plot No. F-11 236, Sector - 3
Planning authority
City and Industrial Development Corporation of Maharashtra
Approved layout land
469.68 sq.m
Land for this registration
469.68 sq.m
Permissible built-up area
1,549.94 sq.m
Registered office
V Times Square
Plot boundaries
North
Plot No - F -10 235
South
Plot No -F- 12 237
East
Plot No -246
West
Proposed 9 Mtr Wide Road
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • YES BANK โ€” 167257
    IFSC YESB0000216
    Ground Floor, Sharda Terraces, Plot No 65, Sector-11, Cbd Belapur, Navi Mumbai, Mumbai, Maharashtra-

Commencement Certificate documents

  • CIDCOBP CC.pdf
  • Latest CC.pdf

Buyer community

Connect with other buyers and owners of Prime Opal โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Prime Opal. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.