PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

BHAVESHWAR RUDRAMahaRERA P52000048978

by RUDRA INFRA

526+527, PUSHPAK NODE, 410206

Dec 2027
Possession
22.5%
Built
0
Complaints
114
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P52000048978
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2026
Construction
22.5% complete
Units sold
66 of 114

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvesting30%
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Jan 2023
Floors
13
Unit mix
102 res ยท 12 comm

Buyer community

Connect with other buyers and owners of BHAVESHWAR RUDRA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching BHAVESHWAR RUDRA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.