Under construction

Divine Hill ViewMahaRERA P52000050970

by Divine Enterprises

Plot No. - 161, Sector No. - 1, Pushpak Node ,Panvel, 410206

Sept 2027
Possession
58.2%
Built
0
Complaints
43
Units
High risk
  • Possession delayed ~1 yr. Originally promised Apr 2026, now proposed Sept 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2027 per the RERA filing.

Official RERA facts

Registration
P52000050970
Status
New
Stage
Certificate Signed
Possession
September 2027originally April 2026
Construction
58.2% complete
Units sold
16 of 43

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
May 2023
Floors
8
Unit mix
36 res ยท 7 comm

Buyer community

Connect with other buyers and owners of Divine Hill View โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Divine Hill View. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.