FLORENCE LANDMARK PHASE 1MahaRERA P52000051375
71/1/B/1, NEAR SUNRISE RESIDENCY, DAMAT, 410101
Dec 2026
Possession
71.2%
Built
0
Complaints
209
Units
Caution
- Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P52000051375
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 71.2% complete
- Units sold
- 80 of 209
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Planting5%
Street Lightingnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Jun 2023
- Floors
- 8
- Unit mix
- 161 res ยท 48 comm
Buyer community
Connect with other buyers and owners of FLORENCE LANDMARK PHASE 1 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching FLORENCE LANDMARK PHASE 1. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.