๐Ÿ—๏ธ
Under construction

TRINITY TOWERSMahaRERA P52000051800

by KARMA CONSTRUCTIONS LLP

Suryey No./CTS No.-16(2) ,16(3) and 17(1), Next to Sudarshan Colony, 402116

Oct 2032
Possession
25%
Built
0
Complaints
144
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52000051800
Status
New
Stage
Certificate Signed
Possession
October 2032
Construction
25% complete
Units sold
0 of 144

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)20%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jul 2023
Floors
13
Unit mix
108 res ยท 36 comm

Buyer community

Connect with other buyers and owners of TRINITY TOWERS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching TRINITY TOWERS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.