Under construction

LAXMI VILLAMahaRERA P52000052296

by SHREESUNDER DEVELOPERS

Plot no 233 Sector 19, ULWE, 410206

Jan 2027
Possession
48.6%
Built
0
Complaints
5
Units
High risk
  • Behind schedule. Possession is due Jan 2027 but construction is only at 48.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2027 per the RERA filing.

Official RERA facts

Registration
P52000052296
Status
New
Stage
Certificate Signed
Possession
January 2027
Construction
48.6% complete
Units sold
2 of 5

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2023
Floors
3
Unit mix
5 res ยท 0 comm
Architect
AR KAUSHAL JADIA

Buyer community

Connect with other buyers and owners of LAXMI VILLA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching LAXMI VILLA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.