Under construction

Wise City RZ-01 Plotted Development - Phase 3MahaRERA P52000052569

by Wadhwa Construction and infrastructure Private Limited

82/4, 82/5, 82/6, 82/7, 82/8, 82/10, 82/3, 82/13, 84/3 (Pt), 84/4 (Pt), 86/1, 86/2, Wadhwa Wise City, 410206

Dec 2026
Possession
โ€”
Built
0
Complaints
104
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52000052569
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
โ€”
Units sold
70 of 104

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water85%
Solid Waste Management And Disposalnot started
Electrical meter room, sub-station, receiving station65%
Aggregate area of recreational Open Spacedone
Open Parkingdone

Building & registration

RERA registered
Sept 2023
Architect
Visionary Design Architects

Buyer community

Connect with other buyers and owners of Wise City RZ-01 Plotted Development - Phase 3 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Wise City RZ-01 Plotted Development - Phase 3. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.