SHREEJI HILLS

by SHREEJI HILLS

Plot No. 11A, Sector-10, Panvel, 410221

High risk
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 76.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.

Official RERA facts

Registration
P52000052626
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
76.4% complete
Units sold
38 of 39

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Open Parkingnot started

Building & registration

RERA registered
Sept 2023
Floors
7
Unit mix
35 res ยท 4 comm

Buyer community

Connect with other buyers and owners of SHREEJI HILLS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHREEJI HILLS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.