Under construction

IVORY ESTATESMahaRERA P52000052665

by NAVOM CREATORS LLP

GAT NO 29/5 AND GAT NO 29/6, BEHIND KRUSHIVAL PRESS, 402209

Dec 2026
Possession
1.8%
Built
0
Complaints
56
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 1.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52000052665
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
1.8% complete
Units sold
12 of 56

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Sept 2023
Floors
8
Unit mix
54 res ยท 2 comm
Architect
MANAJIT MOHITE

Buyer community

Connect with other buyers and owners of IVORY ESTATES โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching IVORY ESTATES. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.