PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

AMBAJI RESIDENCYMahaRERA P52000052731

by VISHAL TUKARAM PATIL

PLOT NO. 41, NODE-PUSHPAK NAGAR, 410206

Jul 2026
Possession
90.9%
Built
0
Complaints
15
Units
Caution
  • Possession delayed ~1 yr. Originally promised May 2025, now proposed Jul 2026 per the RERA filing.

Official RERA facts

Registration
P52000052731
Status
New
Stage
Certificate Signed
Possession
July 2026originally May 2025
Construction
90.9% complete
Units sold
2 of 15

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Sept 2023
Floors
5
Unit mix
15 res ยท 0 comm
Architect
Ankush Rohidas Bhagat

Buyer community

Connect with other buyers and owners of AMBAJI RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AMBAJI RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.