Ambers Dnyaneshwar CapitalMahaRERA P52000052875

by Capital Builders

Plot No -177 , Sector No - 25, Pushpak Node, 410206

Nov 2026
Possession
54.1%
Built
0
Complaints
55
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2026 per the RERA filing.

Official RERA facts

Registration
P52000052875
Status
New
Stage
Certificate Signed
Possession
November 2026
Construction
54.1% complete
Units sold
8 of 55

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Oct 2023
Floors
8
Unit mix
45 res ยท 10 comm
Architect
Destination Architecture Interior Designs

Buyer community

Connect with other buyers and owners of Ambers Dnyaneshwar Capital โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Ambers Dnyaneshwar Capital. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.