Under construction
PRAARAMBH SADANIKAMahaRERA P52000053148
SURVEY NO 57/B/12 NAD 57/B/13, KOLHARE NERAL, 410101
Dec 2026
Possession
66.8%
Built
0
Complaints
28
Units
Caution
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P52000053148
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2025
- Construction
- 66.8% complete
- Units sold
- 6 of 28
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Oct 2023
- Floors
- 6
- Unit mix
- 28 res ยท 0 comm
- Architect
- THE DESIGN INDIA GROUP
Buyer community
Connect with other buyers and owners of PRAARAMBH SADANIKA โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching PRAARAMBH SADANIKA. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.