SHIV SAMARTH ENCLAVEMahaRERA P52000053794

by PATIL INFRACON PRIVATE LIMITED

PLOT NO 19A SECTOR 25A, PUSHPAK NEW WAHAL, 410206

Jun 2026
Possession
78.5%
Built
0
Complaints
42
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 78.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.

Official RERA facts

Registration
P52000053794
Status
New
Stage
Certificate Signed
Possession
June 2026originally December 2025
Construction
78.5% complete
Units sold
20 of 42

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements85%
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Nov 2023
Floors
8
Unit mix
36 res ยท 6 comm
Architect
KALPAK ARCHITECTS

Buyer community

Connect with other buyers and owners of SHIV SAMARTH ENCLAVE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHIV SAMARTH ENCLAVE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.