Under construction

ARC ONEMahaRERA P52000054033

by SURESH GHANSHAMDAS CHHATWANI

PLOT NO B25 AND B26 SECTOR 16 ULWE ULAWE NAVI MUMBAI 410206, ULWE, NAVI MUMBAI, 410206

Dec 2026
Possession
37%
Built
0
Complaints
21
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 37%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52000054033
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
37% complete
Units sold
0 of 21

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)20%
Landscaping & Tree Plantingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Dec 2023
Floors
3
Unit mix
21 res ยท 0 comm
Architect
ATUL PATEL ARCHITECTS

Buyer community

Connect with other buyers and owners of ARC ONE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ARC ONE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.