PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Infragate PalaceMahaRERA P52000054419

by Sharda Infra

Plot No. 262, Sector-3, Dapoli -Pushpak Node, 410206

Dec 2026
Possession
64.2%
Built
0
Complaints
33
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52000054419
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
64.2% complete
Units sold
19 of 33

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains50%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving station50%

Building & registration

RERA registered
Jan 2024
Floors
7
Unit mix
29 res ยท 4 comm
Architect
Disha Architects

Buyer community

Connect with other buyers and owners of Infragate Palace โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Infragate Palace. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.