Possession
83.5%
Built
0
Complaints
39
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Kharghar / PanvelValue

The airport-bet frontier โ€” golf course, hills and heavy new supply.

Growth drivers:
Navi Mumbai International Airport, MTHL access, NAINA planning zone.
Who buys here:
First-time buyers and investors betting on the airport economy.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P52000054880
Status
New
Stage
Certificate Signed
Possession
December 2027
Construction
83.5% complete
Units sold
22 of 39

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Feb 2024
Floors
8
Unit mix
39 res ยท 0 comm
Architect
TRIARCH DESIGN STUDIO

Buyer community

Connect with other buyers and owners of INNOVATIVE CRYSTAL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching INNOVATIVE CRYSTAL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.