HD PRIDEMahaRERA P52000055238
PLOT NO 16 SECTOR 24, TALOJA, 410208
Mar 2027
Possession
32.7%
Built
0
Complaints
149
Units
High risk
- Behind schedule. Possession is due Mar 2027 but construction is only at 32.7%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
Official RERA facts
- Registration
- P52000055238
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027
- Construction
- 32.7% complete
- Units sold
- 36 of 149
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)20%
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvesting40%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Mar 2024
- Floors
- 8
- Unit mix
- 132 res ยท 17 comm
- Architect
- ATUL PATEL ARCHITECTS
Buyer community
Connect with other buyers and owners of HD PRIDE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching HD PRIDE. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.