PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

GAVAND PLAZAMahaRERA P52000055466

by GAVAND PLAZA

SURVEY NO. 500 PLOT NO. 2, ANANDNAGAR, 402107

Jan 2027
Possession
19.5%
Built
0
Complaints
36
Units
Caution
  • Behind schedule. Possession is due Jan 2027 but construction is only at 19.5%.

Official RERA facts

Registration
P52000055466
Status
New
Stage
Certificate Signed
Possession
January 2027
Construction
19.5% complete
Units sold
0 of 36

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply60%
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Storm Water Drainsnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Mar 2024
Floors
8
Unit mix
24 res ยท 12 comm
Architect
PLANET ARCHITECTS

Buyer community

Connect with other buyers and owners of GAVAND PLAZA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GAVAND PLAZA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.