PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

ADITYA RESIDENCYMahaRERA P52000055899

by ADITYA PRAVIN BUILDERS AND DEVELOPER PRIVATE LIMITED

PLOT NO 421 SECTOR 25A, SECTOR-25A WAHAL, 410206

Apr 2027
Possession
27.3%
Built
0
Complaints
17
Units
Caution
  • Behind schedule. Possession is due Apr 2027 but construction is only at 27.3%.

Official RERA facts

Registration
P52000055899
Status
New
Stage
Certificate Signed
Possession
April 2027
Construction
27.3% complete
Units sold
2 of 17

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Apr 2024
Floors
5
Unit mix
15 res ยท 2 comm

Buyer community

Connect with other buyers and owners of ADITYA RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ADITYA RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.