PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SKYWAY ASTERMahaRERA P52000077751

by SKYWAY DEVELOPERS

PLOT NO. 148, NODE- PUSHPAK, 410206

Jun 2027
Possession
75%
Built
0
Complaints
25
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P52000077751
Status
New
Stage
Certificate Signed
Possession
June 2027
Construction
75% complete
Units sold
12 of 25

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving station60%

Building & registration

RERA registered
Oct 2024
Floors
5
Unit mix
20 res ยท 5 comm
Architect
DISHA ARCHITECTS

Buyer community

Connect with other buyers and owners of SKYWAY ASTER โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SKYWAY ASTER. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.