Under construction
Satyam TridentMahaRERA P52000078461
by Satyam Infracon Private Limited
Plot No. 217, Sector-R4, Vadghar, Navi Mumbai, 410206
Dec 2026
Possession
48.2%
Built
0
Complaints
43
Units
High risk
- Behind schedule. Possession is due Dec 2026 but construction is only at 48.2%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P52000078461
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 48.2% complete
- Units sold
- 7 of 43
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Building & registration
- RERA registered
- Dec 2024
- Floors
- 9
- Unit mix
- 38 res ยท 5 comm
- Architect
- Deepak Thakare Architect
Buyer community
Connect with other buyers and owners of Satyam Trident โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Satyam Trident. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.