THE ELYSIAN
GAT NO 174, 177, 178, MULE, 402201
- Possession delayed ~2 yrs. Originally promised Mar 2026, now proposed Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P52000079874
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally March 2026
- Construction
- โ
- Units sold
- 0 of 25
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Possession extension history
- EA08052620876Revised to December 2027
Reason for delay explained in Self Declaration Uploaded in "Others"
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Mar 2025
- Architect
- HARSHAD K HATKAMKAR
- Plot / CTS / survey no.
- GAT NO 174, 177, 178
- Planning authority
- Department of Town Planning & Valutaion
- Approved layout land
- 44,650 sq.m
- Land for this registration
- 44,650 sq.m
- Recreational open space
- 4,351 sq.m
- Permissible built-up area
- 39,079.31 sq.m
- Registered office
- CASABLANCA
- North
- ADJACENT PROPERTY
- South
- RIVER
- East
- VILLAGE ROAD
- West
- RIVER
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- ICICI BANK LIMITED โ 62344IFSC ICIC0000366ICICI Bank Ltd., Nalanda Dance Research Centre, 10Th Road, J.V.P.D, Scheme, Juhu, Vile ParleW, Mumbai.400049
Commencement Certificate documents
- NA Order COMPRESSED.pdf
Buyer community
Connect with other buyers and owners of THE ELYSIAN โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching THE ELYSIAN. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.