ABHIMAAN HOMES PHASE II

by RISING PROPCON LLP

GAT NO 8,12,16,18,19,20, Shirgaon, 412402

May 2022
Possession
88.9%
Built
1
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2019, now proposed May 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (May 2022) has passed with construction at 88.9%.

Official RERA facts

Registration
P52100000285
Status
Ongoing
Stage
Certificate Signed
Possession
May 2022originally December 2019
Construction
88.9% complete
Units sold
0 of 0

RERA complaint record1 record

  • ComplaintCC125021952 Jul 2025
    RISING PROPCON LLP vs Ganesh Jaysing Jadhav

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposal70%
Water conservation /Rain water harvestingdone
Energy managemcnt70%
Fire protection and fire safety requirements75%
Electrical meter room, sub-station, receiving station75%
Aggregate area of recreational Open Spacedone
Open Parking75%

Building & registration

RERA registered
Jul 2017
Floors
14

Buyer community

Connect with other buyers and owners of ABHIMAAN HOMES PHASE II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ABHIMAAN HOMES PHASE II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.