Under construction

Urban Nest Phase1

by VTP Mohite Associates

SNO 58 hissa no 2B sno 58 hissa 2sub hissa no 1 A and sno 58 hissa no2 subhissa 2 A, UNDRI, 411028

Mar 2022
Possession
100%
Built
3
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Mar 2020, now proposed Mar 2022 per the RERA filing.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Mar 2022 per the RERA filing.

Official RERA facts

Registration
P52100000581
Status
Ongoing
Stage
Certificate Signed
Possession
March 2022originally March 2020
Construction
100% complete
Units sold
0 of 0

RERA complaint record3 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jul 2017
Floors
14

Buyer community

Connect with other buyers and owners of Urban Nest Phase1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Urban Nest Phase1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.