Under construction

Godrej Greens

by DREAM WORLD LANDMARKS LLP

Survey no. 31 part , 32 part, 33 part, 34 part, 37 part and 40 part, Undri, 412207

Sept 2026
Possession
100%
Built
26
Complaints
952
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Sept 2022, now proposed Sept 2026 per the RERA filing.
  • 26 RERA complaints. 26 complaint records are disclosed against this project on MahaRERA.

Official RERA facts

Registration
P52100000985
Status
Ongoing
Stage
Certificate Signed
Possession
September 2026originally September 2022
Construction
100% complete
Units sold
835 of 952

RERA complaint record26 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jul 2017
Floors
20
Unit mix
952 res ยท 0 comm
Architect
Architecture Collective

Buyer community

Connect with other buyers and owners of Godrej Greens โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Godrej Greens. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.