Under construction

Skyi Songbirds Phase B

by Enerrgia Skyi Developers

274/1 and others Bhugaon Mulshi Pune, Bhugaon, 412115

May 2022
Possession
85.7%
Built
1
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Nov 2020, now proposed May 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (May 2022) has passed with construction at 85.7%.

Official RERA facts

Registration
P52100001117
Status
Ongoing
Stage
Certificate Signed
Possession
May 2022originally November 2020
Construction
85.7% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting98%
Street Lighting95%
Treatment And Disposal Of Sewage And Sullage Water75%
Solid Waste Management And Disposaldone
Water conservation /Rain water harvesting95%
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Raw Water Supply Schemedone

Building & registration

RERA registered
Jul 2017
Floors
14

Buyer community

Connect with other buyers and owners of Skyi Songbirds Phase B โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Skyi Songbirds Phase B. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.