KAMAL VILLA II

by RAJ HOUSING CORPORATION

KONDHWA S.No 58 HISSA No. 2/4/2A, 5/3B, 7B/1A, 7B/3/1, 7B/3/2, 5/2/30, 2/2, 1/1, 1/1/3, 5/1/1/9, 5/1, Gokulnagar, 411048

Sept 2020
Possession
87.3%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Mar 2019, now proposed Sept 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 87.3%.

Official RERA facts

Registration
P52100001209
Status
Ongoing
Stage
Certificate Signed
Possession
September 2020originally March 2019
Construction
87.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Landscaping & Tree Plantingdone
Street Lightingnot started
Community Buildings50%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Space50%
Open Parkingnot started

Building & registration

RERA registered
Jul 2017
Floors
15

Buyer community

Connect with other buyers and owners of KAMAL VILLA II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching KAMAL VILLA II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.