Under construction

OAKWOOD HILLS

by SHARAD SOPAN SHENDE

26 HISSA NO 3 AND 4, Baner, 411045

Jun 2019
Possession
39.5%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2019) has passed with construction at 39.5%.

Official RERA facts

Registration
P52100001235
Status
Ongoing
Stage
Certificate Signed
Possession
June 2019
Construction
39.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Planting50%
Street Lightingnot started
Community Buildingsdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingnot started
Energy managemcnt50%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station10%
Aggregate area of recreational Open Spacedone
Open Parking50%

Building & registration

RERA registered
Jul 2017
Floors
4

Buyer community

Connect with other buyers and owners of OAKWOOD HILLS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching OAKWOOD HILLS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.