All RERA projects
๐๏ธ
Under construction
Nayantara Heights
697 p F.P number 418-P, Pune (M Corp.), 411037
Dec 2021
Possession
100%
Built
0
Complaints
0
Units
Caution
- Possession delayed ~3 yrs. Originally promised Dec 2018, now proposed Dec 2021 per the RERA filing.
Official RERA facts
- Registration
- P52100001471
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2021originally December 2018
- Construction
- 100% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone
Building & registration
- RERA registered
- Jul 2017
- Floors
- 12
Buyer community
Connect with other buyers and owners of Nayantara Heights โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Nayantara Heights. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.