Under construction

Marvel Brisa

by MARVEL REALTORS AND DEVELOPERS LTD

S No.24/4B, Pune (M Corp.), 411045

Mar 2019
Possession
91.2%
Built
22
Complaints
0
Units
High risk
  • 22 RERA complaints. 22 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 91.2%.

Official RERA facts

Registration
P52100001627
Status
Ongoing
Stage
Certificate Signed
Possession
March 2019
Construction
91.2% complete
Units sold
0 of 0

RERA complaint record22 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths60%
Water Supply45%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drains80%
Landscaping & Tree Planting10%
Street Lightingnot started
Community Buildings50%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting50%
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station35%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jul 2017
Floors
25

Buyer community

Connect with other buyers and owners of Marvel Brisa โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Marvel Brisa. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.