PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Whispering Glades

by Kakade Associates Undri

survey no 59 /1B /1, MOHAMMADWADI, 411028

Jul 2019
Possession
51.5%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jul 2019) has passed with construction at 51.5%.

Official RERA facts

Registration
P52100001890
Status
Ongoing
Stage
Certificate Signed
Possession
July 2019originally July 2018
Construction
51.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supply70%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drainsnot started
Landscaping & Tree Planting50%
Street Lighting50%
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jul 2017
Floors
4

Buyer community

Connect with other buyers and owners of Whispering Glades โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Whispering Glades. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.