Under construction

GRANDBAY A5 A6 B3

by PRAKASH HARAKCHAND PARAKH

S NO 65 PART, PUNE, 412307

Sept 2018
Possession
90.9%
Built
2
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Sept 2018) has passed with construction at 90.9%.

Official RERA facts

Registration
P52100002050
Status
Ongoing
Stage
Certificate Signed
Possession
September 2018originally March 2018
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone
GARBAGE CHUTEdone
GAS BANKdone
PODIUM WITH GARDENdone

Building & registration

RERA registered
Jul 2017
Floors
14

Buyer community

Connect with other buyers and owners of GRANDBAY A5 A6 B3 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GRANDBAY A5 A6 B3. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.