PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SOMANI RESIDENCY

by NITIN PRABHUDAS SOMANI

SURVEY NO 28/4 P TALUKA MULSHI DIST PUNE, Punawale, 411033

Mar 2018
Possession
65%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2018) has passed with construction at 65%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Mar 2018 per the RERA filing.

Official RERA facts

Registration
P52100002216
Status
Ongoing
Stage
Certificate Signed
Possession
March 2018
Construction
65% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jul 2017
Floors
33

Buyer community

Connect with other buyers and owners of SOMANI RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SOMANI RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.