PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

ONE MALL

by NIRMAN PROPERTIES

SURVEY NO 22/2 RAVET, Pimpri Chinchawad (M Corp.), 412101

Dec 2019
Possession
42.7%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 42.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2019 per the RERA filing.

Official RERA facts

Registration
P52100002399
Status
Ongoing
Stage
Certificate Signed
Possession
December 2019originally December 2018
Construction
42.7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station80%
Open Parking80%

Building & registration

RERA registered
Jul 2017
Floors
7

Buyer community

Connect with other buyers and owners of ONE MALL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ONE MALL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.