PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Tinsel County Phase I

by Grow India Realcon LLP

41/5, PUNE, 411057

Feb 2021
Possession
100%
Built
1
Complaints
0
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52100002596
Status
New
Stage
Certificate Signed
Possession
February 2021
Construction
100% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting50%
Street Lighting50%
Treatment And Disposal Of Sewage And Sullage Water80%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting60%
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Space70%
Open Parkingdone

Building & registration

RERA registered
Aug 2017
Floors
15

Buyer community

Connect with other buyers and owners of Tinsel County Phase I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Tinsel County Phase I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.