Under construction

SAI PARADISE

by Haresh Premchand Chandwani

S NO 52/4/1/4,6,8,18,22 BANER, Baner, 411045

Dec 2021
Possession
72.6%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 72.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2021 per the RERA filing.

Official RERA facts

Registration
P52100002660
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021
Construction
72.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths70%
Water Supply70%
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Storm Water Drains70%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water70%
Solid Waste Management And Disposal70%
Water conservation /Rain water harvesting90%
Energy managemcnt90%
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station90%
Open Parking70%

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of SAI PARADISE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAI PARADISE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.