Under construction

THE RIDGES PHASE I

by VENKATESHWARA ASSOCIATES

385/1, Bhugaon, 412115

Aug 2019
Possession
41.8%
Built
7
Complaints
0
Units
High risk
  • Recovery warrant issued. MahaRERA has issued 1 recovery warrant against this project โ€” the strongest enforcement action on record.
  • 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Aug 2019) has passed with construction at 41.8%.

Official RERA facts

Registration
P52100003060
Status
Ongoing
Stage
Certificate Signed
Possession
August 2019
Construction
41.8% complete
Units sold
0 of 0

RERA complaint record7 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths80%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drains80%
Landscaping & Tree Planting25%
Street Lighting10%
Community Buildings10%
Water conservation /Rain water harvesting80%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Space25%

Building & registration

RERA registered
Aug 2017
Floors
3

Buyer community

Connect with other buyers and owners of THE RIDGES PHASE I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching THE RIDGES PHASE I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.