Dec 2026
Possession
50%
Built
1
Complaints
114
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52100003084
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2024
Construction
50% complete
Units sold
97 of 114

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths92%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drains96%
Landscaping & Tree Planting72%
Street Lighting92%
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposaldone
Water conservation /Rain water harvesting70%
Energy managemcnt69%
Electrical meter room, sub-station, receiving station77%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
2
Unit mix
114 res ยท 0 comm
Architect
Minaj Magdum

Buyer community

Connect with other buyers and owners of Amoda Reserve - South Park โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Amoda Reserve - South Park. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.