Under construction
Guardian Eastern Meadows - Phase 2
by Guardian Promoters & Developers Private Limited
Plot A, Gat No. 1344/1/1 and 1344/1/2, Haveli, 412207
Dec 2026
Possession
62.3%
Built
5
Complaints
227
Units
High risk
- Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Dec 2026 per the RERA filing.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P52100003157
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2022
- Construction
- 62.3% complete
- Units sold
- 147 of 227
RERA complaint record5 records
- ComplaintCC1260141614 Mar 2026ASMITA ASHWINKUMAR HATWAR vs Guardian Promoters & Developers Private Limited
- ComplaintCC1260100924 Feb 2026SHIVKUMAR SINGH PUNDIR vs Guardian Promoters & Developers Private Limited
- ComplaintCC0050000001066345 Mar 2022Proposed Guardian Eastern Meadows CHS vs Guardian Promoters & Developers Pvt. Ltd. though Mr. Manish Murlidhar SabadeOrder of Guardian CHS.pdf on MahaRERA
- ComplaintCC00500000009596720 Sept 2021Mrs. Shraddha Jitendra Dolare before Marriage Miss Shraddha Madhukar Hingase vs Guardian Promoters & Developers Private Ltd. Thr. its Directors a. Manish Sabade b. Manish SomanOrder of Shraddha Dolare-3-08-2023.pdf on MahaRERA
- ComplaintCC00500000001070116 Dec 2017Mahesh Vilasrao Dube vs Guardian Promoters and Developers Private LimitedCC 005 10701 Mahesh Vilasrao Dube.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposal50%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 15
- Unit mix
- 227 res ยท 0 comm
- Architect
- Vikas Achalkar Vikas Achalkar
Buyer community
Connect with other buyers and owners of Guardian Eastern Meadows - Phase 2 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Guardian Eastern Meadows - Phase 2. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.