Under construction

WESTBROOK

by Tara Constructions

4-1, 4-2-1, 4-2-2, 4-2-3, AMBEGAON, 411046

May 2024
Possession
68%
Built
14
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Sept 2020, now proposed May 2024 per the RERA filing.
  • 14 RERA complaints. 14 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (May 2024) has passed with construction at 68%.

Official RERA facts

Registration
P52100003178
Status
Ongoing
Stage
Certificate Signed
Possession
May 2024originally September 2020
Construction
68% complete
Units sold
0 of 0

RERA complaint record14 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingdone
Street Lightingnot started
Community Buildingsdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
14

Buyer community

Connect with other buyers and owners of WESTBROOK โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching WESTBROOK. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.