Mar 2027
Possession
90.9%
Built
1
Complaints
125
Units
High risk
- Possession delayed ~7 yrs. Originally promised Dec 2019, now proposed Mar 2027 per the RERA filing.
Official RERA facts
- Registration
- P52100003198
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2027originally December 2019
- Construction
- 90.9% complete
- Units sold
- 58 of 125
RERA complaint record1 record
- ComplaintCC00500000009629118 Jan 2022Adv.Surekha Bhagwat vs Mr.Amit Dnyaneshwar Daware and Mr.Sawami Vishnu YelwandeOrder of Surekha Bhagwat.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone
Building & registration
- RERA registered
- Aug 2017
- Floors
- 18
- Unit mix
- 117 res ยท 8 comm
Buyer community
Connect with other buyers and owners of AMRUTVEL โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching AMRUTVEL. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.