  • Possession delayed ~6 yrs. Originally promised Jun 2019, now proposed Dec 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 96.8%.

Official RERA facts

Registration
P52100003300
Status
Ongoing
Stage
Certificate Signed
Possession
December 2024originally June 2019
Construction
96.8% complete
Units sold
0 of 0

RERA complaint record1 record

  • ComplaintCC124003475 Oct 2024
    Alka Singh vs The Kings Way AOP

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supply85%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains90%
Landscaping & Tree Planting90%
Street Lightingdone
Community Buildings85%
Treatment And Disposal Of Sewage And Sullage Water80%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting80%
Energy managemcnt80%
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Space70%

Building & registration

RERA registered
Aug 2017
Floors
15

Buyer community

Connect with other buyers and owners of The Kings Way - A1, A2 and A3 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching The Kings Way - A1, A2 and A3. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.