SINHGAD PLANET B WING

by ANANT NARAYAN GANDALE

31/10/1, 31/10/2,31/10/3,31/11, NARHE, 411041

Apr 2021
Possession
27.3%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Oct 2019, now proposed Apr 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Apr 2021) has passed with construction at 27.3%.

Official RERA facts

Registration
P52100003473
Status
Ongoing
Stage
Certificate Signed
Possession
April 2021originally October 2019
Construction
27.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
7

Buyer community

Connect with other buyers and owners of SINHGAD PLANET B WING โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SINHGAD PLANET B WING. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.