PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

DIVINE MIST

by V & T Properties

S NO 108/1/2, Kalewadi Rahatani, 411017

Sept 2022
Possession
73.5%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Feb 2021, now proposed Sept 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2022) has passed with construction at 73.5%.

Official RERA facts

Registration
P52100003638
Status
Ongoing
Stage
Certificate Signed
Possession
September 2022originally February 2021
Construction
73.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply60%
Sewerage (Chamber, Lines, Septic Tank , STP)65%
Storm Water Drains65%
Landscaping & Tree Plantingdone
Water conservation /Rain water harvesting65%
Electrical meter room, sub-station, receiving station75%
COMMON AREA LIGHTING60%

Building & registration

RERA registered
Aug 2017
Floors
5

Buyer community

Connect with other buyers and owners of DIVINE MIST โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching DIVINE MIST. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.