PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

FEEL BLISS PHASE-I

by Maple Ravima Realtors

SR. No. 33/20 B, Bavdhan, 411021

Sept 2020
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Mar 2019, now proposed Sept 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2020 per the RERA filing.

Official RERA facts

Registration
P52100003782
Status
Ongoing
Stage
Certificate Signed
Possession
September 2020originally March 2019
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Street Lightingdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Entrance lobbydone

Building & registration

RERA registered
Aug 2017
Floors
14

Buyer community

Connect with other buyers and owners of FEEL BLISS PHASE-I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching FEEL BLISS PHASE-I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.