Under construction

LIFE VILLE

by BHARAT SITARAM KATE

154 P, 155 1, 155 3, 156 1, 156 3, 158, 159, 156 2, 156 5, Pimpale Saudagar, 411027

Mar 2019
Possession
30.2%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 30.2%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Mar 2019 per the RERA filing.

Official RERA facts

Registration
P52100003879
Status
Ongoing
Stage
Certificate Signed
Possession
March 2019
Construction
30.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
17

Buyer community

Connect with other buyers and owners of LIFE VILLE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching LIFE VILLE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.