Jun 2023
Possession
58.2%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~3 yrs. Originally promised Jul 2020, now proposed Jun 2023 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 58.2%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2023 per the RERA filing.
Official RERA facts
- Registration
- P52100004048
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2023originally July 2020
- Construction
- 58.2% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 5
Buyer community
Connect with other buyers and owners of VISHNU KRUPA โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching VISHNU KRUPA. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.