PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

V3 VINAMRA

by V3 INNOVATORS

71A 71C 1 71C 1 1C 1D 5 AND 71 4 11 D, MANJARI Bk, 412307

Jun 2018
Possession
56.8%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2018) has passed with construction at 56.8%.

Official RERA facts

Registration
P52100004156
Status
Ongoing
Stage
Certificate Signed
Possession
June 2018
Construction
56.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains50%
Landscaping & Tree Plantingdone
Water conservation /Rain water harvesting50%
Electrical meter room, sub-station, receiving station20%
Aggregate area of recreational Open Spacedone
Open Parking90%

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of V3 VINAMRA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching V3 VINAMRA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.