PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Aseemvishwa

by JAYANT HARI MULAY

CTS No 3184 Part S No 172/3, Chinchwad, 411033

May 2024
Possession
100%
Built
3
Complaints
0
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Oct 2019, now proposed May 2024 per the RERA filing.

Official RERA facts

Registration
P52100004207
Status
Ongoing
Stage
Certificate Signed
Possession
May 2024originally October 2019
Construction
100% complete
Units sold
0 of 0

RERA complaint record3 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone

Building & registration

RERA registered
Aug 2017
Floors
16

Buyer community

Connect with other buyers and owners of Aseemvishwa โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Aseemvishwa. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.