Under construction

ACROPOLIS

by KRRISHA DEVELOPERS

108/3B CTS 6075/6076, Pune, 411017

Mar 2021
Possession
100%
Built
0
Complaints
0
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2018, now proposed Mar 2021 per the RERA filing.

Official RERA facts

Registration
P52100004298
Status
Ongoing
Stage
Certificate Signed
Possession
March 2021originally December 2018
Construction
100% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingdone
Street Lightingdone
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
SOLAR SYSYTEMnot started

Building & registration

RERA registered
Aug 2017
Floors
13

Buyer community

Connect with other buyers and owners of ACROPOLIS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ACROPOLIS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.